December Construction Update (2019)

December Construction Update (2019)

East Side: Slab on grade pours are complete on the south side of the site. On the North side, slab pours continue and WB is currently preparing for the first pours at Parking Level 1 - they expect to be at the ground floor in January which is very exciting!

West Side: Vertical drilling for shoring is complete with exception of the Tunnel connecting to E1. Excavation for this parcel will not begin until the spring of 2020.

The 610 Markham House move is now slated for early January. This will be a huge endeavour with more information to come.